Roof Replacement: Set the Decking Change-Order Rule
Quick Answer: Agree how concealed roof-deck damage will be documented, priced, and approved when exposed during full replacement.
On this page
Applicability and model notes
This is an on-site hidden-condition decision during an already authorized whole-roof project; it is distinct from comparing complete bids and from diagnosing an active leak.
- Decking type, replacement unit, included allowance and price basis must match the signed project documents. A homeowner cannot determine panel soundness by walking or probing a roof deck.
Symptom checks
The roofer reports damaged sheathing after tear-off
First check: Ask for the exposed location, photos, quantity and the contract definition or allowance that applies before approving added work.
A change order lists a lump sum without quantity or unit price
First check: Request the measurement basis, unit price, included disposal/fasteners and any separate fascia or framing charges in writing.
Diagnostic Checks
Roof Replacement
Tools needed: Signed proposal or work order, Phone camera, Room, wall or roof checklist
- Before tear-off, ask the contractor to define what counts as unsound decking and require notice before work beyond the included allowance proceeds, except immediate temporary weather protection. What to look for: Both sides know when concealed damage becomes a change request.
- Put the unit price and measurement basis for replacement sheathing in the signed work order; ask how partial panels, fasteners, disposal, fascia or framing are priced separately. What to look for: A written price formula exists before the deck is exposed.
- Ask for dated photos of exposed damage and replaced areas, quantities used, and your written approval before they are covered when practical. Keep change orders with the original contract. What to look for: The concealed work has a record you can reconcile against the final invoice.
Stop and get qualified help when
Do not access the roof; ask for photos and the roofer’s documented assessment.
Require the contractor to make the area temporarily weather-tight while documenting the change.
How to Check the Result
- Before work proceeds beyond the signed allowance, confirm the location, quantity, unit-price calculation and written authorization are recorded; permit immediate temporary weather protection while the scope is clarified.
- At invoice review, reconcile each replaced sheet/panel and any separately priced fascia or framing work with dated photos and approved change orders.
Professional repairs
Roofing contractor or project manager
Have the person authorizing the work document concealed deck conditions, quantity, unit price, and approval before replacement where practical.
Community discussions
These are individual reports, not verified repair instructions. Outcomes may not apply to your equipment.
The full roof project uncovered a scope or product mismatch after work began.
Attempted: A homeowner compared the signed contract with work performed and contacted the contractor after discovering that old skylights and an attic fan had been reinstalled.
The contractor said the new skylights were the wrong size and would be custom ordered; the thread does not confirm final correction.
When this may apply: Use as one homeowner-reported project example only; it does not establish market prices, code compliance, or a universally correct installation method.
Frequently asked questions
Should I approve the whole decking allowance before tear-off?
References & sources
-
Asphalt Shingle RoofsBuilding America Solution Center, Pacific Northwest National Laboratory
Applies to: Asphalt-shingle roof replacement; verify local code, climate, product instructions, and roof assembly.
Retrofit and installation scope, roof deck and flashing; ensuring success and professional contractor/permit checks.
-
Company I hired messed upReddit · r/roofing
Applies to: A public homeowner report illustrates the described project and reported outcome only; it is not construction authority or an independently verified technical inspection.
A homeowner reported a full-roof contract that included skylights and a fan, then found old units reinstalled after the crew said the replacements were incorrectly sized; the thread records a scope/documentation gap, not a deck repair outcome.