Tub-to-Shower Quote: Compare the Drain and Waterproofing Scope
Quick Answer: Compare tub-to-shower bids by the complete water-control assembly, not just tile, wall panels or the visible shower base. Each quote should identify what is removed, drain and waste work, the receptor or shower-floor system, wall substrate, one named waterproofing method and its seams, corners, penetrations and transitions, the pre-finish water test, permits, and the process for hidden damage. Ask how the proposed system connects to the drain and terminates at the bathroom floor. Tile and grout alone do not describe a waterproof shower.
On this page
Applicability and model notes
For planning and comparing written bids to remove a bathtub and build a stand-alone shower. This is project procurement and assembly-scope review, not troubleshooting an existing leak or a shower installation walkthrough.
- A tiled shower uses a system-specific waterproofing assembly. The substrate, membrane, drain connection, seams, corners, valve/head penetrations, curb or threshold and floor-to-wall transitions must work together.
- A prefabricated receptor or direct-to-stud surround may use a different assembly. Require the bid to name the manufacturer's complete product system and installation details.
- Drain size, trap, venting, route, slope, framing, accessibility and permit requirements depend on the home and local code. The licensed plumber and local authority must confirm them.
Symptom checks
Bids differ but describe waterproofing vaguely
First check: Ask each bidder to list the exact system, every included layer and transition, and the inspection/test milestone before finish.
The proposal keeps existing tile or joins a new shower base below it
First check: Ask how new water protection connects continuously to the existing assembly and who accepts responsibility for that concealed transition.
The old tub drain stays in place or plumbing scope is unclear
First check: Ask the plumber to identify the proposed shower drain location, waste and trap work, access, permit and code assumptions.
Planning the replacement floor around a new shower
First check: Coordinate finished floor height and transitions with the remodel scope.
Diagnostic Checks
Request the same written scope from every bidder
Tools needed: Room photos and approximate dimensions, A copy of each written proposal, 25-foot tape measure for approximate planning dimensions
- Ask each bidder to mark demolition limits: tub, surround, wallboard/backer, floor finish, subfloor access, plumbing access and disposal. Request separate allowances for hidden rot, mold-like growth, damaged framing or suspect materials, with stop-and-approve before extra work. Record approximate room dimensions for the same quote brief only where safely accessible. Do not remove fixtures or finishes to measure; ask bidders to verify the room, framing, plumbing, and product dimensions on site. What to look for: Bids use the same boundary and explain what happens if concealed conditions differ.
- Have the plumbing scope name the shower drain/receptor location, expected waste, trap and vent changes, valve work, access/repair, inspection and permit responsibility. Ask the plumber to confirm the arrangement against local code after inspecting the site. What to look for: Tub-drain assumptions and code-sensitive work are visible in every proposal.
- For tile, ask the contractor to name one manufacturer-supported assembly and identify its substrate, pan or sloped base, membrane, drain interface, seams, corners, penetrations, curb/threshold, niche or bench, and wall-to-floor transition. For a prefabricated pan or wall kit, request the exact model and instructions for its wall-to-pan seal and finish details. What to look for: The quote describes a continuous system matched to its drain and finish. 'Cement board and tile' alone does not specify waterproofing.
- Ask for a hold point to inspect the receptor and waterproofing before finish covers it. Specify the manufacturer's applicable water/flood test, cure time, inspection sign-off, documentation and what happens if it fails. What to look for: Water-control work is reviewed while visible. Test procedure and code requirements depend on the chosen system and local authority.
Compare the whole bid and its change-order rules
- Mark demo, disposal, drain and valve, substrate repair, waterproofing products/layers, receptor, tile or panel finish, enclosure, permits, inspections, water test, cleanup, warranty and schedule as included, excluded or allowance. What to look for: Differences reveal whether bidders priced different finishes, omitted plumbing/testing, or assumed different hidden conditions.
- Ask each contractor: 'Show where the shower waterproofing connects to the drain, bathroom floor, wall finish and any existing material that stays.' Request the manufacturer's detail when a joint is not self-explanatory. What to look for: The bid addresses interfaces instead of relying on grout, caulk or appearance as the only water barrier.
- Get in writing who selects and installs each component, obtains permits/inspection, prices and approves concealed damage, documents the test, and handles workmanship and manufacturer warranties. What to look for: You can compare accountability and the hidden-condition process before work starts.
Stop and get qualified help when
Request a complete water-control assembly and manufacturer-compatible transitions in writing before comparing or signing.
Ask for a continuous assembly or a clear written limitation before work.
Do not scrape, sand, cut or remove it until a qualified asbestos professional assesses it.
Have licensed trades confirm structural, trade, permit and accessibility requirements for the property.
How to Check the Result
- Before signing, every bid identifies the same work boundary, named system, drain approach, test/inspection milestone, allowances and exclusions.
- During work, request documentation of the drain connection, seams and transitions before covering; the qualified installer follows the selected manufacturer's procedure.
- At handover, retain product names, manuals, permits/inspection records, test documents and warranty terms.
Tools & replacement parts
Tool
25-foot tape measure for rough project dimensions
Fits: Use only for safe, approximate, accessible room, opening, or patio dimensions in the quote brief; contractor must verify all dimensions before design or ordering.
Check your model manual before ordering. Search results do not confirm compatibility.
As an Amazon Associate I earn from qualifying purchases.
Professional repairs
Bathroom remodel contractor
Provide a written scope, named system, transition details, pre-finish inspection/test milestone, exclusions and change-order procedure.
Licensed plumber
Confirm shower drain, waste, trap, vent, valve and permit requirements for the property and local code.
Building department or inspector
Confirm permits, inspections and tests for this conversion and selected assembly.
Community discussions
These are individual reports, not verified repair instructions. Outcomes may not apply to your equipment.
A New England homeowner received different bids for a tub-to-shower conversion and questioned what the price included.
Attempted: The homeowner compared proposals listing demolition to studs, plumbing updates, acrylic pan and walls, valve, shower head and sliding doors, and considered hiring a contractor while choosing tile independently.
The post documents scope uncertainty but no final selection or completed job. It supports requesting comparable bids; its prices are not a market benchmark.
When this may apply: Use this as a prompt for a same-scope comparison; verify system, drain, testing, permits and local cost independently.
A homeowner wanted to remove an acrylic tub while keeping recent tile and joining a shower base below it.
Attempted: The poster proposed removing one tile row for a new waterproofing overlap and asked for experience.
Replies highlighted the old/new waterproofing interface and drain work. No construction or verified outcome is reported.
When this may apply: Make the transition and responsibility explicit in the quote; do not treat a commenter's proposed detail as a verified assembly.
Frequently asked questions
Are tile or grout the waterproofing?
Can a new shower base simply meet the old tub surround tile?
Should both quotes include the same water test?
Which related planning guides should I read?
References & sources
-
Schluter-Shower System Installation HandbookSchluter Systems
Applies to: Schluter Shower System; other products need their own manufacturer instructions.
System instructions cover membrane, drain, seams, floor/wall transitions and recommend a water test before tile with cure timing. Applies only to Schluter assemblies.
-
I’m remodeling my home. Do I need to be concerned about asbestos in the building materials?U.S. Environmental Protection Agency
Applies to: Suspect material that may be disturbed by renovation.
Appearance cannot identify suspect material; use a trained/accredited professional before disturbing it.
-
How to Waterproof a ShowerOatey
Applies to: General planning context; Oatey product and local requirements govern installation.
Manufacturer overview distinguishes waterproofing from tile/grout and discusses drain, wall and floor connections. Use the exact products' current instructions.
-
Tub to walk-in shower conversionReddit · r/BathroomRemodeling
Applies to: Illustrates why quotes should identify transition and drain. Commenters' code assertions are not authoritative requirements.
Homeowner asks whether a tub can be removed while keeping recently installed tile and joining a shower base below it; replies identify old/new waterproofing tie-in and drain as project risks. Proposed project only, no completed outcome.
-
Tub to shower conversionReddit · r/homeowners
Applies to: First-hand quote comparison only; regional dated prices are not a market benchmark.
Original poster in New England describes two bids for one 30×60×96 conversion and lists demo to studs, plumbing update, acrylic pan and walls, valve, shower head and sliding door. The homeowner is still deciding; comments debate finish and scope. No general price inference.